New Bedford has roadwork sites for the upcoming week of April 15, 2024 – April 19, 2024

image_pdfimage_print

“The City of New Bedford has roadwork sites for the upcoming week of April 15, 2024 – April 19, 2024, and they are as follows:

City offices will be closed on Monday, April 15th in observation of Patriot’s Day

Eversource will be working on gas main relays and services on:

• Main relay on Acushnet Ave from Phillips Rd to Bowles St
• Main relay on Acushnet Ave from Phillips Rd to 3082 Acushnet Ave
• Main relay on Brook St from Irvington St to Clifford St
• Main relay on County St from Cove St to Rivet St
• Main relay on Princeton St from Church St to Ashley Blvd
• Services on Central Ave from Church St to Conduit St
• Services on Jouvette St from County St to Crapo St
• Services on W. Rodney French Blvd from Calumet St to Bayview St
• Test holes on Church St from Park Ave to Nash Rd

Other:

• Contractor (Barletta Heavy Division) scheduled to start night work at future pedestrian bridge across Rte 18. Starting Sunday, April 16th through Thursday, April 19th MassDOT will be closing Acushnet Avenue, Rte 18 Northbound, Rte 18 Southbound and the Purchase Street Ramp during overnight hours from 8:00PM to 5:00AM for one night each segment. Traffic detours will be in place. 
• Contractor (PA Landers) will be working on a road reconstruction project at West Rodney French Boulevard from Cove Street to George Street. Overnight sewer work at the intersection of Warren St scheduled for Tuesday night into Wednesday morning.  
• Contractor (JH Lynch) will be working on the MassDOT road construction project at the intersection of Rockdale Avenue at Allen Street Traffic detours will be in place during workday hours of operation.
• Contractor (various utility companies) will be working on utility pole transfers at the MassDOT road construction project on Kings Highway from Mt. Pleasant Street to Oliver Street.
• Contractor (PA Landers) scheduled to commence work on Monday, April 15th at the MassDOT road reconstruction project on County Street from Nelson Street to Rivet Street.
• Contractor (Various utility companies) will be working on utility pole transfers at the MassDOT road reconstruction project on Acushnet Avenue from Tobey Street to Pequot Street.
• MassDOT will be staging installation and beam end cleaning and concrete encasements at I-195 East and West bound lanes over Purchase Street, County Street and State Street. Work will take place Sunday – Thursday with overnight operations only.
• Contractor (SCR Constructors) will continue site work at the future South Coast Rail station platform locations in the city. (Church Street at Carlisle Street and Wamsutta Street at Acushnet Avenue.) and continue site work at future pedestrian bridge across Route 18 impacting parking along Purchase Street between Willis Street and Pearl Street and at the Division of Career Services on Acushnet Avenue. If you have questions, please email the project team at SouthCoastRail@dot.state.ma.us
• MassDOT scheduled to start pavement preservation and related work on Route 140 both northbound and southbound from mile marker 0.0 to mile marker 5.2 starting April 1st and is scheduled until January 15th, 2026. Work to be conducted during overnight hours. Police details and ramp closures with detours to be expected.
 
Project: Lead Service Line Replacement Program Phase II   General Contractor: C. Naughton Corp. (Monday-Friday 7:00am -5:00pm)
• The contractor will be working Lead Service Line Replacements. Tuesday on Clover Street between Allen Street and Grape Street, Allen Street between Winter Street and Brownell Street. Wednesday on Short Street between Allen Street and Grape Street. Thursday on Field Street between Allen Street and Grape Street, Short Street between Allen Street and Grape Street. Friday on Oak Street between Allen Street and Grape Street. At times during working hours, these locations may be closed to thru traffic with signs posted to detour traffic around work areas. Police details will be on-site allowing access to residents only and assisting with traffic management.

Project: Grape Street Collector Rehabilitation General Contractor: Green Mountain Pipeline Services Subcontractor: Duke’s Root Control and Ribeiro Construction Inc (Friday 7:00 AM to 4:00 PM)
• The Subcontractor is scheduled to continue installation of the drain manhole and 36-in PVC drain piping at Buttonwood Park between the pond and Kempton Street.

Project: Phase 4 Transmission Main Reinforcement Project   Contractor: C. Naughton Corp. (Monday-Friday 7:00 AM to 4:00 PM)
• The Contractor will continue replacing a section of the existing 48-in water transmission main north of the railroad crossing at Chipaway Road in East Freetown.

Project: Shawmut Avenue and Howland Street Pumping Station Improvements Project General Contractor: WES Construction Corp. (Monday-Friday 7:00 AM to 4:00 PM)
• The contractor is scheduled to continue installation of granite curb and concrete sidewalk replacement along Nash Road between Shawmut Avenue and Mount Pleasant Street. Lane restrictions will be in place during working hours, with one lane of alternating traffic open. Police officers will be on-site to assist with traffic management.”-City of New Bedford.

About Michael Silvia

Served 20 years in the United States Air Force. Owner of New Bedford Guide.

Check Also

New Bedford Police arrest three, seize firearm after north-end incident

“NEW BEDFORD – Patrol officers have taken an illegal firearm off the streets and placed …

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Translate »