New Bedford has roadwork sites for the upcoming week of July 3, 2023 – July 7, 2023

“The City of New Bedford has roadwork sites for the upcoming week of July 3, 2023 – July 7, 2023, and they are as follows:

City offices will be closed on Tuesday, July 4th!

Eversource will be working on gas main relays and services on:

• Main relay on Church St from Wood St headed South to Carlisle St.
• Main relay/regulator on corner of Potter St and Rockdale Ave headed East towards Nashua St.
• Main relay on Pinette St from Brownell Ave to Town Line
• Main relay on Brownell Ave from Hawthorn St to Gaywood St
• Main relay on Rockdale Ave from Allen St to Bluefield St
• Abandonment on West Rodney French Blvd from Welcome St to Grit St.

Other:

• Contractor (PA Landers) will continue sidewalk work at the road reconstruction project on Clifford St from Acushnet Ave to Ashley Blvd.
• Contractor (PA Landers) will be working at the intersection of County St x Union St. Lane closures and detours to be in place.
• Contractor (PA Landers) will continue sidewalk work on Phillips Rd from Holly Tree Lane to Monica’s Way. Minor traffic impacts and lane shifts required.
• Contractors (PA Landers and various utility companies) will be working at MassDOT’s Kings Highway project. Minor traffic impacts and lane shifts required.
• Contractor (PA Landers) will be working at MassDOT project #609201, located at the intersection of Acushnet Ave & Peckham Rd/Sassaquin Ave.
• Contractor (PA Landers) will be working on West Street from Allen Street to Priscilla Street and on Priscilla Street from West Street to Brigham Street on sidewalk work and road reconstruction in preparation for final top course paving.
• PA Landers will be working on Elm Street from Pleasant Street to Purchase Street, Purchase Street from Elm Street to Middle Street, Middle Street from Purchase Street to Fredrick Douglass Blvd, and Fredrick Douglass Blvd from Middle Street to Elm Street.
• Contractor (Indus) will be applying an asphalt emulsion to the roadways at the following locations, NO PARKING may be required in areas and will be posted by notice on orange construction cones:
◦ Acushnet Ave – Wamsutta St to Logan St
◦ Birchwood Dr – Phillips Rd to Longview Rd
◦ Brownell Ave – Carroll St to Allen St
◦ Forbes St – Acushnet Ave to end
◦ Hathaway Blvd – Rockdale Ave to Parker St
◦ Hollytree Ln – Phillips Rd to Greenbrier Dr
◦ Logan St – Acushnet Ave to Howe St
◦ Maxfield St – Lindsey St to Liberty St
◦ Mill St – Rockdale Ave to Pleasant St
◦ Orchard St – Hawthorn St to Arnold St
• Contractor (SCR Constructors) will continue site work at the future South Coast Rail station platform locations in the city. (Church St at Carlisle St and Wamsutta St at Acushnet Ave.) If you have questions, please email the project team at SouthCoastRail@dot.state.ma.us
• Contractor (SCR Constructors) will continue site work at the future pedestrian bridge across Route 18 impacting parking along Purchase Street between Willis Street and Pearl Street and at the Division of Career Services on Acushnet Avenue. Temporary detours may be in place pending construction activities occurring.  If you have questions, please email the project team at SouthCoastRail@dot.state.ma.us.” -City of New Bedford.